Project Status

Reporting
Period
Project
Name
Project
Code
Team Project
Leader
Client
Liaison
Monitored by
IT PMO
March, 2009 APP Enhancements ABC App Development     Yes

Project Description

This project will update the blah blah blah to the current corporate standard (Oracle 10g, release 2) as well as provide enhancements to the user interface / functionality as requested by the end users.

Overall Project Status

Overall Status At A Glance Explanation of Issue (if applicable)
Schedule - Will the project be completed on time? Project taken off hold
Budget - Will the project be completed within budget?  
Resources - Are the proper people and infrastructure available?  
QA/QC - Will the project deliverable be completed within acceptable quality levels?  
Change Notices - Are scope change requests being managed successfully?  
Issues - Are the project issues being addressed successfully?  
Risks - Are project risks being successfully managed?  
Communications - Are all stakeholder concerns being addressed successfully?  

Legend:
- No issues exist or issues are being addressed and are under control.
- There is an issue, current or emerging, which may impact the project if not addressed.
- There is an issue that has impacted the project negatively. Immediate action required.

Budget & Costs

AFE Original Budget Current Budget Total Spent Forecast
ABC123 $216,900.00 $216,900.00 $187,995 $216,900.00
Total $216,900.00 $216,900.00 $187,995 $216,900.00

Project Milestones

Phase Milestone Planned Delivery Date % Complete
Initiate     100%
  Project Initiated 2007-09-01 100%
  Project Kickoff 2008-01-08 100%
  PSR Complete 2008-04-30 100%
  Project Statement Approved 2008-04-30 100%
  Project Schedule Completed 2008-07-31 100%
Plan     100%
  Requirements Approved 2008-04-30 100%
  Project Plan Approved 2008-05-31 100%
  Design Document Complete 2008-09-30 100%
  Design Approved 2008-09-30 100%
Execute     51%
  Perl Enhancements 2008-07-31 100%
  APP Reporter (Java) 2009-03-15 100%
  APP Data Entry (Java) 2009-04-30 100%
  Testing & development re-work 2009-05-31 25%
  APP (Java) Environment Integration 2009-06-30 0%
  Project In-Service 2009-06-30 0%
Close     0%
  Project Transitioned to Support 2009-08-31 0%
  Project Complete 2009-08-31 0%
  Total Project Completion 2009-08-31 63%

Additional Information

Key Activities

This Reporting Period

  • Point 1
    • Subpoint 1
  • Point 2
    1. Subpoint X
    2. Subpoint Y

Next Reporting Period

  • Meeting with XYZ to discuss the project scope, milestones, deliverable, budget, and time lines
  • Continue development and developer testing